Don't divide tasks between people
View Single Post
Lizard
Omni
2007-03-14, 09:32 AM
Lizard
View Public Profile
Send a private message to Lizard
Find all posts by Lizard
If you assign both resources to the parent task at 100%, but adjust their working hours (in calendar view) to, say, 40 hrs/week and 10 hrs/week, then level, Fred will get 4 times as much of the work as John.