View Single Post
I believe we fixed the issue of some Google calendars not showing up in OmniPlan 2.2.4. Google made some back end changes that violated assumptions we should not have made in the first place. I wonder though if the problem erichv is describing is the same. We'd need more specifics of what you're trying to do. Contacting support directly is probably your best bet.

If you are subscribing to free/busy, it's worth noting that this is never going to populate a resource's schedule with working time. It will really just take away time that the calendar server reports as busy for the resource.

Tom