Just to make things a little clearer...we started using Omniplan in September and put in ten major task groupings etc. All looks good, however, the end date shows February when we know it should be January. The project actually started in August, so what I want to do change the start date to August. When I do that, the tasks don't change their dates though.

Ultimately, I was hoping that Omniplan could show us an ever-updating End date - in other words, if we're ahead of time on some tasks, the end date would automatically come forward and if we're behind, the end date would show as being pushed back. Maybe this is not the right tool for this sort of planning or maybe we're doing something wrong?