View Single Post
Oh Fantastic!!! Thank you! That was as easy as I expected it would be - I just couldn't find it.

I wonder if I could ask a follow-up question. Once I have done this I want to move the group of tasks to an earlier date by about 1 week. When I try to do this the blue group does not move but rather a grey line is created extending backwards to the date I have selected.

What does this grey area mean? a change from the original plan? How do I move the item without the grey line?

Thank you!!!!

Al