Hi All,

New to omnifocus. was previously using ms project and ms outlook (parallels) and I could make any task dependent on any other task or group of tasks being completed first.

How do i achieve this in omnifocus? I've searched an havent found anything that really address this.

I have three situations that this usually comes up. project "2" is dependent on project "1" being finished. or task "b" in project "2" is dependent on a specific task in project 1 being finished first or task "b" in project "2" is dependent on the entire project 1 being finished first.

any suggestions are greatly appreciated