Another way to customize tasks based on who is assigned, is to create a named Style for that resource. To do that, open the Project: Style Inspector, then create a new named Style with the + button. Make the style choices you'd like, i.e. Background color, gantt bar color, completion bar color, font color, etc...

Now, grab that Style row and drag it onto a Resource in the Resource View. Or, highlight the resource and press the function key assigned to that named style (the first is always F1). Any existing or new Tasks assigned to that Resource will now get that style.