I agree with you. But at the same time, there are really two types of Critical Paths people want to see. First they want to seethe critical path for timeline just like it is currently. But we also want to see the critical path that is the path is has the direct line of dependents back to project start regardless of timelines. Point is that if there was a weeks worth of wiggle room/slack or even a hour. We should be able to tell OP to disregard that. I should be able to see the CP without any concern for slack.

On a side bar would be nice if we could add a default lead time for activities. As realistically no one will ever finish on project and start the other immediately. There is ALWAYS a delay. wether it be 10min or 2 hours.