View Single Post
Its easter and I am trying to learn omniplan using the trial with a view to buying later.

I work in government where there are certain meeting dates where parts of a project will be approved along the way.

These types of dates cant be changed, eg report to senior management meeting or council meeting that are on fixed dates along the way

I seem to be able to fix a start or end date but not dates along the way and omniplan tends to work out the quickest path from there.

Can you let me know if its possible to start from a certain date, specify the end date which is essentially the date where my final work is endorsed and the fixed meetings where sub approvals will occur along the way.