My question is related to rescheduling a group of tasks.
I created a reasonably complex task structure and grouped tasks in groups.
When I try to reschedule a group of tasks by changing the group attributes in the inspector, it changes start and end dates for the group only, not for the underlying tasks. How can I move the whole group of connected tasks in time? It will take me otherwise a day to move them and their dependances individually one by one.

Thanks!