View Single Post
Sequential takes precedence over the due date in the available view setting in my experience. A tasks with a due date is not considered available if it is preceded by another tasks in a sequential list regardless of its due/overdue status. If possible, can you set the project or a subsection of the project to parallel and let their availability be controlled by the due dates? There could be many ways to address varying structures using a combination of sequential and parallel functionality. Otherwise, if this is not possible, you would probably need to setup a custom perspective to allow you to view buried tasks which are due in sequential lists.