Quote:
Originally Posted by CTYankee View Post
I then go to the Configure Publishing and Subscriptions menu in the project, chose the people, assign the iCal calendar to the person, select 'events are off hours'....and nothing.
Hi! Just to be clear, after you set up this subscription action, did you perform an Update? This is under the Project menu, or Cmd-Ctrl-U. It doesn't happen automatically unless you check the box at the bottom of that sheet.

If you were able to Update without error, and the tasks are still on "off" days, could you double check the Calendar View, select the resource in question, and click "Extra & Off Hours" in the mini calendar? This will confirm that the events are coming in properly.

Hope this helps,

Joel R