View Single Post
I am using Omniplan again after a long break....

I imported an MPP file to start with. Many of the durations are showing up with hours and days ... e.g. 1d 7h. I change it to 1d and it changes back. I have the project set to daily scheduling. It looks silly with all of these tasks showing hours.

What am I missing here?

Thanks