View Single Post
Quote:
Originally Posted by Anita View Post
How does get the start date set automatically for repeating tasks? At the moment whenever I mark complete a repeating task (which has a start date) it creates a new task with a due date but no start date. I have to manually set the start date to get it off my available actions list.
Hm, for me this is working: I set a start date (03.01.2008), a due date (04.01.2008), Repeat from completion day every 1 week, and the Action Inspector tells me the time of the next task, if I mark "complete": Next Start 09.01.2008, next Due 10.01.2008. I don't have to set the start date manually, and the task is not shown, as the starting time is tomorrow.