View Single Post
Quote:
Originally Posted by michaelatSPG View Post
I thought it'd be fine to just use tasks as projects (and subtasks as tasks) to handle the multiple-projects issue.

The only downside I see so far is that Critical Path will not work properly, since it looks over the whole file instead of for each task separately...
And what would one use as subtasks? ;-)

Let's hope Omni fixes all of this sooner than later. If they integrate Plan Focus, Graffle and Outliner, then they might have a grand slam, or a real OmniDazzle.