I have set the baseline for all of the tasks. I am now updating my project plan by entering the logged hours and "start" and "end" dates and times for the tasks completed.

For example :

Developer 1 was suppose to start on Task # 38 on June 16 and finish June 17. The duration for the task was 4 hours. Developer 1 did not start ticket # 38 until June 20 and did not finish until June 23. Developer 1 logged 3.0 hours for that task instead of the original estimate of 4.

When I enter the start date under "Start" as June 20, and enter the "End" as June 23, it re-adjusts the hours allotted for that task making it 12 hours instead of 4 and vice versa, when entering the correct number of hours he worked, it adjust the "End " date.

Would someone be able to provide a solution for updating a project plan created in Omniplan. I am new to Omniplan.

Thank you.