On a similar note, I am trying to reschedule the start of a project to August, as we were not using Omniplan at the time. I want to see the correct end date. However, when I change the start date of the project, the first task does not change to this new start date, even though all tasks are set to start "As Early As Possible" - so even though I've pulled back the start date by a month, the end date doesn't come back by a month. Is this a bug or am I doing something wrong?

Thanks for any advice
Gavin