Originally Posted by pvonk View Post
If the 15 chapters must be reviewed by a certain date (perhaps your boss expects a report), then create a project with that due date. Then enter each of the 15 chapters as individual actions, in the right order.
That is easy to do. But I have lots of projects that don't have a due date, or at least they can slide. For instance, I want to turn the lecture notes of a class I just taught into a book. I can take half a year for that, I can take a whole year. So I want to enter tasks "do section A, do section B" a week apart, but in case something urgent comes up I want to be able to move the whole project back by a week or two.

Quote:
It sounds like you're trying to have OF remind you periodically to read a certain chapter. What you need is to have "Read chapter 1" permanently on you list of things to do until you check it off.
Right. But the task "read chapter 2" should not come up until a few days after chapter 1 is completed.

Victor.