Thread: Durations
View Single Post
You want the duration to be fixed, and the effort to vary with the amount of resources assigned. So put two weeks in the duration field, and make sure the little people icon next to the duration is light gray and the effort one is dark gray.

If you assign the resources first, and then set up durations it should help you work around the fact that different people work different numbers of hours per week.