View Single Post
Quote:
Originally Posted by Greg Jones View Post
raffo,

Next Action: Just what it says, the very next action (task) in an active project.

Available: Tasks in a project that are not blocked by other tasks (in a sequential project) and tasks that are not blocked by a later start date. In a sequential project:

>Task A
>Task B
>Task C

Task B will not appear as available until Task A is completed. If Task B has a start date in the future, it will not appear as available until that date, even if Task A is completed today.

Remaining: Any task that has not been completed, regardless of its available (blocked) status.
thanks!

so, if i have just sequential projects with no later start date, "next" and "available" show the same events... :)