So I am new to OmniPlan. I have used several tools in the past, but like the simplicity of omniplan. One critical feature I cannot figure out how to do is to reschedule the work on a task that is incomplete when there is completed % entered on the task...

Example: I have a task "Do Stuff", this task was originally scheduled for a duration of 10 days, on 5/5/08 - 5/16/08. 50% of the task is complete (5 days completed), and I want to reschedule the remaining 50% for past the current date, so ideally it would fall from 5/21 - 5/27 (5 days work left). However, when rescheduling in OmniPlan it moves the whole 10 day task.

Now it does not show work in the resource view for the completed part, it it includes it as part of the leveling so no other work is assigned for the completed part.

This causes several holes in the plan from a work perspective when updating the plan and rescheduling uncompleted work.

Any suggestions?