I have "daily scheduling" selected in the project inspector, but when I type "2w" or "5w" for the duration of some tasks, they automatically convert to a duration of "2w 2h" or "5w 7h" (for example).

I have the normal work schedule defined as simply 8-5 M-F so I don't understand why it is adding some number of hours to the tasks.