View Single Post
I have a resource assigned to 6:30 pm to 9:30 pm schedule and another one with the same availability.

One task that requires both will take 3 hrs to complete, another will take 2 hrs.

However, OmniPlan is scheduling the tasks for mid-afternoon starting at 2:30.

This makes no sense. I've double checked assignments and schedules and re-leveled.

Any ideas? Thanks in advance!