Hi - I did submit a bug report for this earlier today.
The date problem is there pre-export, within OmniPlan itself. The project has a start date (May 18, 2006), but the app filled in an end date of 9/1/74 4:14 AM. I don't see any way to change this.
I also notice that one of the tasks within the project has been assigned this same date and I can't change it. All the other tasks look fine.
Update - I just deleted that task an created it again and the problem is not there now.
PEBCAK? I dunno. Very weird though.