Originally Posted by jkolonay
I too am attempting to use OmniPlan to manage multiple projects. So far, I have a group for each active project. I have a limited number of developers and for planning purposes, I assume that 10% of their day is lost to rest room breaks, phone calls, etc. So I start with a base 90% for each developer.

What I'm wondering is how do I make this work to say Developer A will spend 45% of their day on tasks in project A and 45% of their day on tasks in project B between date 1 and date 2. Is this possible currently?

Thanks for the great mac software! I'm an M$ Project refugee :)
You should be able to change the assigned percentage amount by selecting the task or group that the resource is assigned to and change their assigned percentage in the "Task : Assignment" inspector panel.