View Single Post
I'm doing a remodel and the room happens to be available 24x7x365, so I've tried entering the 'room' as an 'equipment' resrource, with a normal work week calendar of 24x7.

I have a test to perform in the room that takes 60 (minimum) to 72 (maximum) hours to perform. (In separate tasks, I set up and tear down the test myself; the 60 hours does not involve me at all.) I've created a task and assigned it to the 'room' resource. After the test is complete, I can then take the results to a place and get the results. I'm not able to figure out how to enter, for example, 60 hours. I've tried effort and duration and nothing seems to work (I get much larger numbers).

I know I have some learnin' to do, but any tips would be appreciated.

Bob

Last edited by omnibob; 2009-11-03 at 01:42 PM..