View Single Post
Please add my vote as well!

Omniplan beats other PM tool in terms of ease of use but this is a show stopper for me. I need to be able to specify the duration of a task and then the amount of effort required. If I then add a resource, I would expect the programme to calculate the % utilisation per day for that resource. So a 10 day task (duration) with 5 days of effort would yield 50% utilisation per day for one resource (if the Resource is given 100% availability).

In this way I can utilise the resource on other tasks at the same time. If the total assignment exceeds 100% at any given point then a small hand will appear and show me the error of my ways...