Hi all

I'm evaluating omniplan for my work and started a test project.
I created a few resources (3 employees and 1 "tool" which is actually a conference room). The conference room is only available on mondays so I changed the availability to mondays only in the calendar view.
I assigned a few tasks to this resource and thought omniplan would schedule these tasks to mondays only but it's not. Looks like it doesn't care what's set in the availability for this resource?
Would be great if someone could help me with this, I'm probably doing something wrong?

Thank you

olivero