When using Microsoft Project I could set one task with a duration, for example 2 weeks. I could then set another task as dependent on that one but specify that it was due to start part way through the other... [task1 FS - 1week].. (task 1's finish date minus 1 week).

How can I do this in Omni Plan? How can I specify overlapping tasks that are also dependent tasks?

Thanks //:)