Just wanted to tell you that I found a solution to my problem. What I had to do was to assign a 'start date' to the project to be the same as the next available task. Then it wont be shown in my perspective until I need to see it. If there is no tasks available but I know it will arrive, I just put the project on hold.

Not sure if there is an easier way to do it (preferably automatic assign project start date to the same as the next available task?) but this works for now to keep my perspectives clutter free.

Hope this could help someone with the same question as me and if you have any better solutions don't hesitate to post them!

Best
Gus