Originally Posted by pslade View Post
I have noticed the same thing. If I resource someone at 20% on one task and 80% on another the leveling won't allow them to occur concurrently. However, if I change it to 19% instead of 20% it will work fine.
Does this happen in OmniPlan 1.5 pslade? I just tried a simple test project with two tasks, one with a 20% assignment and one with a 80% assignment and leveling allowed them to be scheduled concurrently. Send in your project file to omniplan@omnigroup.com if you're still seeing this problem. Thanks!