Hello
I'm a newbie, which will probably explain my problem.

I have created an omniplan project which has repetitive tasks (the creation of banners and pages for a website). These repetitive tasks are grouped into sections.

A section once completed is released. In my opinion section 2 can begin before section 1 has been completed because they are independent of each other, though they do share resource. I made sure the resource did not overlap either.

So I finished my plan, removed all violations and the completion time came in at 3 months. I was happy. That is until I hit the 'level' button. Now everything has moved and the competition time is 4 months.

Before each section took 5w 3d 3.25h. Now after levelling the sections durations have changed, here are the before and after times.


Before
  • 2w 2d 4.5h
  • 3w 3h
  • 5w 2d 3.5h
  • 5w 3d 3.75h
  • 5w 3d 3.25h
  • 5w 3d 3.25h
  • 5w 3d 3.25h
  • 5w 3d 3.25h
  • 5w 3d 3.25h

After
  • 2w 2d 3.75h
  • 3w 3d 2.75h
  • 7w 3.5h
  • 9w 3h
  • 8w 3.25h
  • 8w 2d 7.5h
  • 9w 1d 3h
  • 9w 2d 5.25h
  • 10w 2d 6.5h

I guess my only way to work out what is going on is to go through it with a fine tooth comb. Which I plan to do later this afternoon

However each section has around a 100 sub tasks so I wanted to ask you, if you have seen this kind of behaviour before?

I would love to attach the plans to this post but they are highly confidential :-(