I'm adding selective calendar export for ofexport so that you'd be able to choose which projects and/or which date ranges you want in an ics file. You could even send different projects/folders to different calendars (which is what I want).

I've got a basic implementation working (not released yet) and items are appearing in the calendar (woohoo!).

However I wouldn't mind a few suggestions on what's sensible in these circumstances:
  • Would you want project/task group to appear as well as it's sub-tasks?
  • Would you want an event to span from it's start to it's due time?
  • What if a task only had a start or a due?
  • Would you want the notes in the event (might make the file large)?