I've done this before but here it is again.

Set a repeat to be any subset of specific days of the week, examples include every MWF, every T TH, only on Saturdays etc. Set repeats to be every weekday or every weekend day or every Sunday or combinations of the above. Set due dates as above.

Set a repeat based on day of month not specific date. Examples include Every 1st and 3rd Tuesday or every 3rd Saturday or Last Monday of the month. Or the first weekend of the month or the last or first weekday or 3rd weekday.

Set repeats based on quarters. So something could be set to be due 4 times a year on the 1st Wednesday of the quarter. Or started once a quarter on the second weekend of the quarter.

Set repeats based on half year items. As above

Setting flexible repeats that include both start and due dates. Start again X days after finish and then due x days after start. Or by the days of the week or by day of month not specific date or by quarter or half year as above. So you could do something like repeat item X starting on the 1st Monday of each month and due 2nd Friday of each month. Or start something first weekday of the quarter and due by the last weekday of the quarter.

As I said it was incredibly flexible and very powerful. Basically any way you could think of how to handle repeating actions was supported.

I miss that. I often have things that used all of the above ways of setting repeats and the OF method is totally inadequate.