View Single Post
Quote:
Originally Posted by mr_projects View Post
I'd like to show an example, as well as the attached file

all tasks are attached together with F->S links, in this example B is 100% complete ahead of schedule, when leveling, it doesn't adjust C accordingly. I hope you got my point
In this situation, we'd recommend setting the end date of Task B to when it was completed. With the dependency connection between Task B and C, Task C won't start right after Task A because it has to start right after Task B's "Finish to Start" connection.

If you remove the connection between Task B and Task C (provided that all tasks are assigned to the same resource), you'll see Task C being leveled to start right after Task A like you wanted it to.

So for now, you should either change the end date of Task B or remove the dependency connection between Task B and Task C. I've filed a feature request in our database for an easier way to mark a task completed "today" and to automatically set the end date to reflect that.