Here's what I think is a bug. In preferences I have 3 pm as the default due time for actions (under the data tab). If I create a new action and assign it a due date it will be due at 3 pm. So far, so good.

If I make the action a repeating action, then if "Repeat From: Assigned Date" is checked, when I complete the action, the next action also becomes due at 3 pm on the appropriate day. Excellent, that's just what I expect. However, if "Repeat From: Completion Date" is checked, when I complete the action, the next action becomes due at 12 am, not 3 pm. So the preference I've set only works for repeating actions if "Repeat From: Assigned Date" is used, not if "Repeat From: Completion Date". That seems like a bug to me.

Note: I'm talking about repeat intervals of one day or more.