Cumulative Days in Gantt Chart
View Single Post
Lizard
Omni
2007-08-13, 09:38 AM
Lizard
View Public Profile
Send a private message to Lizard
Find all posts by Lizard
Not sure it's exactly what you're after, but this might help.
1) Open the Project: Information inspector
2) Change the Start: to "Undetermined Date"
This will change the headings to things like "Day 17" and "Week 3"