Quote:
Originally Posted by Lizard
I'm not quite sure I understand what you're seeing. In my (admittedly simple) check just now, it seems to be working properly.
The field with the dark people icon next to it is the one that will change when the assigned resources change.
So if effort varies with resources assigned, then adding a second resource to an eight hour task will make the effort 16h while keeping the duration at 8h.

But if duration varies with resources assigned, then adding a second resource to an eight hour task will make the duration 4h while keeping the effort at 8h.

Let me know if you're still seeing the issue and maybe more specifics about how you're getting there.
This is the behavior I expect, but instead I find that changing resources assigned changes the duration against a fixed effort value, regardless of which icon is darkened. Is that not what you get? I find this behavior even in a brand new document.