Under the project inspector there is a Styles tab where you'll find styles for a variety of gantt entries, including tasks, milestones, and groups. Select one and these can be modified with the Appearance inspector.

If you want to override the behavior for the class of entry, the Appearance inspector will also modify a selection in the Gantt chart instead of the Project: Styles inspector.

This information is kind of wildly spread around right now - I'm in the middle of a rewrite that should simplify it and group it closer together.

Finally, the ability to turn off the date display of your milestone is found in view options under Gantt Chart, intuitively labeled "Assigned Resources". I'm thinking perhaps we should have a separate setting for milestone date and any other textual information we might display for other entry classes.