Tom --

Thanks for the bar colour formatting advice. I hadn't realised the Gantt Bar colour could be set for a selection: I thought it applied to the whole chart.

Quote:
Originally Posted by Tom Bunch
Finally, the ability to turn off the date display of your milestone is found in view options under Gantt Chart, intuitively labeled "Assigned Resources". I'm thinking perhaps we should have a separate setting for milestone date and any other textual information we might display for other entry classes.-Tom
I had the assigned resources ticked on, so as to show who's working on which bits of the project. That was good.

I strongly agree on the separate settings for the milestone (kilometer-stone?) text and other info. At this point, it's all or nothing.