If there is no shared timelines between the projects, it's probably better to put them in seperate projects with each having the resources limited to the times you described. Since one project is just weekends & the other is just weekdays, this is fine. Alternatively in a single project file, you could setup duplicate resources like Me (Weekday) & Me (Weekend). Then setup distinct schedules for each of those resources.