View Single Post
Here's my example:

TASK LIST

1) "Post ad to Craigslist - day 0" (15m) (Resource - ME)
2) "Let ad run" (Unassigned)
3) "Check email for replies to ad and repost if necessary - day 1" (15m) (Resource - ME)
4) "Let ad run" (Unassigned)
5) "Check email for replies to ad and repost if necessary - day 2" (15m) (Resource - ME)

When I level it, I WANT this all to adjust based on MY availability, with the "Let ad run" task adjusting effort accordingly.

What is the best way to achieve that?

Thank you in advance for your input!

Nathan