Originally Posted by alansg
While it might be considered a workaround, I've been setting the Assigned Amount for a resource assigned to a task to the level-of-effort being applied to the project by that resource.

So, if I want to commit a resource to "1 hour per day" on a particular task, I assign 12% (of an 8-hour day [approx]) of the resource to that task.
Thanks, I have experimented with this too, and it seems to show promise of working well. Will need to research it further.