i just bought Omniplan 2.2 and unfortunately it continuously crashes and has some unpredictable behaviour.

In creating a new project and back filling the line items. The issue that is killing me ATM is OmniPlan decides to start a task on todays date albeit the project date is from December 1st.

Its decided that this particular task cant start before todays date and not the date I want. It's driving me nuts.

When I try to change the start date for the task it just puts the grey line in front of the task although there are no constraints the I can see.

What makes it more annoying is that it is only doing it for a particular group of tasks


I cant change the date in the Task:schedule actual start time. it allws me to enter a date but when I exit the filed it changes the date back to todays date.

How get this to work?

thanks