Yeah, I thought that would work, too. Then I tried it :-)

Okay, here's Joe's plate of work, unleveled and unassigned, with the two "projects" being Budget and Site Preparation:



Now we build the filters for Budget and Site Preparation, use them to select all the tasks in each "project", assign them to Joe, and put him at 50%.






Now we level the document, and look what happens!



That's exactly what the leveling rules say will happen, of course — the stuff higher in the document with equal priority comes first. Unfortunately, what Joe probably wants is to ping-pong between those two projects at the same time, spending half of his time on each, like you can see in the attachment (it would be nice if the limit of inline attachments could be higher!)
Attached Thumbnails
Click image for larger version

Name:	Screen shot 2011-04-29 at 11.38.11 AM.png