I'm using Applescript to update the Completed property of a task. My automated time-tracking system collects and reports work completed in decimal hours.

While I can easily compute the OmniPlan task's Completed as a percentage of planned effort (at the expense of an extra apple event to fetch the planned effort value), it seems to me it would be more straightforward to be able to enter Completed as actual hours instead of as a percentage.

This would seem to me to make sense for manual data input, too, since I suspect many organizations collect actuals information in raw hours.

Perhaps this could someday be a per-task preference? I'd even like to see a project-wide preference for recording actuals as hours or percentages, with the ability to override that setting on a specific task (there are tasks I'm not tracking this closely).