View Single Post
You assigned the meal to one task. Therefore, that is one use of the meal. OmniPlan really doesn't have a clean way to handle this. You could make "Meal" into an equipment resource with a cost of $6.25/hour (or whatever, to work out to $50/day). However, that would mean that if the guy works 3 days + 1 hour on the 4th day, the cost would be $156.25, which may or may not be how your compensation calculations work.