Set the project up with a 24/7 working schedule. Then put in a restricted work schedule for the weeks of the preparation stages that only allows your "normal" work week. Or do it the other way around, adding extra hours/days to the schedule during the event. This can all be done on a resource-by-resource basis; fortunately, you can also edit multiple resources simultaneously by selecting them together before editing.