Have you looked at the resource utilization view (View->Resource View)? That will show if any resources are overcommitted, as seen in the attached example. Note that leveling the project will tend to undo any overcommitments unless there are enough constraints to force a particular solution. Without the constraints on the example, leveling would spread the tasks over 3 days.