Hi

Thanks to the forums I've managed to locate where I can set the start date for the whole project, however the plan I'm trying to re-use is 3 years old, so my calendar now has 3 years of blank gantt chart preceding my new start date. I think the problem is caused by numerous tasks still anchored to their original start dates, hence they now show as violations.

How do I bring these up to date without editing each individual task?

Many thanks

james