From your description is sounds like you created an action to "Subscribe to iCal calendar: X" and imported the events as Off Hours into your Project schedule.

You're absolutely right, it's a total pain to find those exceptions and delete them. They're already imported to the file so getting rid of your subscription doesn't help.

At the moment the only UI for this is to go to the calendar, make sure no resource is selected so that you're viewing the project schedule, click on the "Extra & Off Hours" segment in the lower left, and scrub the project for exceptions one week at a time. Days with exceptions change from green to blue in the small calendar down in the corner, so it doesn't take long to scrub through a whole year. You can select the calendar blocks you need to get right of and delete them w/ the delete key, or get rid of all exception for the week by clicking the (x) in the upper right where it will say "Customized from project's normal work week".

That said, if you delete these subscriptions, or delete or move events from the subscribed calendars and update, the schedule exceptions should be updated to match. Sounds like we ought to re-test that?

-Tom